Thank youfor participating in engagement activities for the 66 Street concept plan, engagement for the concept plan is now finished.
Multiple options for the 66 Street and Yellowhead Trail intersection and the surrounding road network have been considered by our technical team over the last year and many engaged citizens participated in the process.
Please see thephase 3 What We Heard Report, whichprovides a review of Phase 3 engagement and how public and stakeholder feedback in the previous two phases led to the design of the final concept. A video of the Final Concept is also available in the menu on the right.
Thank youfor participating in engagement activities for the 66 Street concept plan, engagement for the concept plan is now finished.
Multiple options for the 66 Street and Yellowhead Trail intersection and the surrounding road network have been considered by our technical team over the last year and many engaged citizens participated in the process.
Please see thephase 3 What We Heard Report, whichprovides a review of Phase 3 engagement and how public and stakeholder feedback in the previous two phases led to the design of the final concept. A video of the Final Concept is also available in the menu on the right.
82 Street to 50 Street: 66 Street Concept Plan has finished this stage
As a part of the strategic plan, the access to and across Yellowhead Trail at 66 Street is planned for closure, which includes the removal of traffic signals. Alternate access to surrounding properties will be reviewed as part of concept planning.
Concept 2018-2019
82 Street to 50 Street: 66 Street Concept Plan is currently at this stage
Developing a plan for what will be built and what it will look like, including changes to the broader roadway network.
Design (Preliminary and Detailed) 2021-2023
this is an upcoming stage for 82 Street to 50 Street: 66 Street Concept Plan
Preliminary: Develop the concept plan in more detail, determine issues and constraints and how those can be managed. Prepare schedule and budget.
Detailed: Refine the preliminary design and prepare plans and specifications that will guide construction and ensure that changes are built to standards.
Build 2024-2025
this is an upcoming stage for 82 Street to 50 Street: 66 Street Concept Plan
Construction will start in 2024, beginning with roadway changes off Yellowhead Trail.
Operate 2025
this is an upcoming stage for 82 Street to 50 Street: 66 Street Concept Plan
Construction will be completed. The area will be fully open for use in its new form.